Lift Refurbishment Works – Start Date

Wandsworth Council have announced the dates when the Lift Refurbishment works will begin. The letter will be circulated to all residents.

Key points

  • The contractor has advised that they propose to start these works on Tuesday 29th August 2023
  • Each lift will be out of action for approximately 12 weeks
Lift Ref Start Date Completion date
Lift C: H116 29th August 2023 27th November 2023
Lift B: H115 28th November 2023 27th February 2024
Lift A: H114 28th February 2024 20th May 2024

If you have any mobility or access issues whilst these works are taking place, please can you contact the CO-OP Management team on 0207 924 5213.

If the event of an emergency, please can you contact Joint Control Centre on 020 8871 7490 which is fully staffed 24 hours/7 days a week.

The lift department can be contacted on 020 8871 7042 Monday to Friday between the hours of 9.00am to 5.00pm

Full Notice: Goulden House – Residents Letter 24th July 2023