Notice to residents – Refurbishment of Main Entrance A – Commencing on Monday 20th April.

Please be advised that refurbishment works will be carried out to the Main Entrance A (Winders Road). During this period, access routes will be temporarily adjusted as outlined below.

PHASE 1 – STARTING MONDAY 20TH APRIL.

  • The section from Main Entrance A to the back door will be closed.
  • Lift access will remain available via the back entrance, accessed through the inner green.

PHASE 2 – STARTING MONDAY 27TH APRIL.

  • Main Entrance A will reopen.
  • Lift access will now be via Main Entrance A only.
  • The back entrance leading to Inner Green will be closed during this phase.

COMPLETION

  • All works are scheduled to be completed by FRIDAY 1ST MAY.
  • A post-inspection will be carried out by the Estate Manager and the Chair of the Management Committee, thereafter.

IMPORTANT NOTES

  • Lift access will be maintained at all times via one entrance route.
  • Some disruption is unavoidable during these works.

We appreciate your patience while improvements are carried out.