Notice to residents – Refurbishment of Main Entrance A – Commencing on Monday 20th April.

Please be advised that refurbishment works will be carried out to the Main Entrance A (Winders Road). During this period, access routes will be temporarily adjusted as outlined below.
PHASE 1 – STARTING MONDAY 20TH APRIL.
- The section from Main Entrance A to the back door will be closed.
- Lift access will remain available via the back entrance, accessed through the inner green.
PHASE 2 – STARTING MONDAY 27TH APRIL.
- Main Entrance A will reopen.
- Lift access will now be via Main Entrance A only.
- The back entrance leading to Inner Green will be closed during this phase.
COMPLETION
- All works are scheduled to be completed by FRIDAY 1ST MAY.
- A post-inspection will be carried out by the Estate Manager and the Chair of the Management Committee, thereafter.
IMPORTANT NOTES
- Lift access will be maintained at all times via one entrance route.
- Some disruption is unavoidable during these works.
We appreciate your patience while improvements are carried out.